The last two weeks have been spent finishing walls and bringing in truckloads (and truckloads and truckloads) of dirt for filling the pool area and for house foundation pad. This had to take place before the font of house foundation footing could be dug and font stem wall built. Still waiting on final survey before the front wall (over 120 feet of wall) can be built. Materials for front wall footing are on site. New dirt had to be trucked in for foundation as existing dirt did not pass compaction testing. Existing dirt was used as fill dirt for backfilling walls.