Excavation for house pad should be complete by end of weekend or by early next week at the latest. Request for surveyors has been made which -depending on the surveyor’s schedule- should be completed by the end of next week or early the following week. Once surveyed, the house footings can be dug, foundation can be formed, and plumbing can be added. This should take around two weeks. Once foundation is formed and plumbing is complete, the foundation can be inspected. Once the foundation passes inspection the pad can be poured (one day) and construction on the house can begin. With this schedule -and no unforeseen delays- framing the house should begin towards the end of October on early November.