Digging and grading for new walls

May 13, 2024 by ckmc

Back wall footing has been approved for pour which is scheduled for Tuesday. Back wall build should start by end of week or early next week. Footings for additional walls were also dug this last week and once rebar placement has been completed, they will be ready for inspection later this week.