Back block wall will be completed by Tuesday. Inspection for concrete fill set for later this week.
Archives for May 2024
Concrete for back wall poured
Footing for the back wall has been poured. Block wall building starts this week.
Digging and grading for new walls
Back wall footing has been approved for pour which is scheduled for Tuesday. Back wall build should start by end of week or early next week. Footings for additional walls were also dug this last week and once rebar placement has been completed, they will be ready for inspection later this week.