Back wall under construction

May 27, 2024 by ckmc

Back block wall will be completed by Tuesday. Inspection for concrete fill set for later this week.

Resized_1000001966_1716850822393
Resized_1000001959_1716850850811
Resized_20240525_094431_1716850809139
previous arrow
next arrow

Filed Under: Povinelli Home Build

Concrete for back wall poured

May 16, 2024 by ckmc

Footing for the back wall has been poured. Block wall building starts this week.

Resized_20240514_124204_1715873153928
Resized_20240514_124153_1715873102218
Resized_20240514_124228_1715873197328
previous arrow
next arrow

Filed Under: Povinelli Home Build

Digging and grading for new walls

May 13, 2024 by ckmc

Back wall footing has been approved for pour which is scheduled for Tuesday. Back wall build should start by end of week or early next week. Footings for additional walls were also dug this last week and once rebar placement has been completed, they will be ready for inspection later this week.

Resized_20240507_092535_1715560388812
Resized_20240507_092415_1715560365878
Resized_20240507_092423_1715560341737
previous arrow
next arrow

Filed Under: Povinelli Home Build